Room to grow

Safe spaces. A growing school.

Improve sanitation, prepare three new classrooms and secure the school grounds.

The need

The school has three classrooms and two latrines according to the project brief. The priority is four additional sanitation units, with separate facilities for girls and boys, accessible entry and handwashing.

The proposed response

Prepare a technical assessment and quotations for sanitation. Then plan a building for three upper-primary classes, furniture, fencing and improvements to the school grounds.

Next steps

  1. 01

    Sanitation assessment and comparable quotations

  2. 02

    Technical approval, funding allocation and maintenance

  3. 03

    Building proposal for the 2027 school year

Who will benefit?

The Beog-Zaadba school community. Scope and beneficiary numbers will be approved for each stage before launch.

Budget explained

A transparent planning basis.

The figures below are estimates, not approved fundraising targets.

Planning assumptions as of 1 October 2026 · FCFA (XOF)
NeedBaseContingencyIndicative total
ASanitation4 100 000410 0004 510 000
BThree-classroom building31 950 0004 792 50036 742 500
CFence and school grounds8 258 0001 238 7009 496 700
DClassroom furniture3 630 000363 0003 993 000

Indicative amounts as of 1 October 2026, including contingencies. Quotations and approval are required before fundraising. Secured resources are not yet known.

Sanitation priority: 4,510,000 FCFA. Building and furniture: 40,735,500 FCFA. Fundraising dates and quotations are not yet approved.