Room to grow
Safe spaces. A growing school.
Improve sanitation, prepare three new classrooms and secure the school grounds.
The need
The school has three classrooms and two latrines according to the project brief. The priority is four additional sanitation units, with separate facilities for girls and boys, accessible entry and handwashing.
The proposed response
Prepare a technical assessment and quotations for sanitation. Then plan a building for three upper-primary classes, furniture, fencing and improvements to the school grounds.
Next steps
- 01
Sanitation assessment and comparable quotations
- 02
Technical approval, funding allocation and maintenance
- 03
Building proposal for the 2027 school year
Who will benefit?
The Beog-Zaadba school community. Scope and beneficiary numbers will be approved for each stage before launch.
Budget explained
A transparent planning basis.
The figures below are estimates, not approved fundraising targets.
| Need | Base | Contingency | Indicative total |
|---|---|---|---|
| ASanitation | 4 100 000 | 410 000 | 4 510 000 |
| BThree-classroom building | 31 950 000 | 4 792 500 | 36 742 500 |
| CFence and school grounds | 8 258 000 | 1 238 700 | 9 496 700 |
| DClassroom furniture | 3 630 000 | 363 000 | 3 993 000 |
Indicative amounts as of 1 October 2026, including contingencies. Quotations and approval are required before fundraising. Secured resources are not yet known.
Sanitation priority: 4,510,000 FCFA. Building and furniture: 40,735,500 FCFA. Fundraising dates and quotations are not yet approved.
View the full programme and assumptionsProject updates
The first steps are being prepared.
No fundraising or new work is confirmed on this page. Approved updates and documents will be published here.